Tasks

Grex's to-dos, action items for outside firms and what Lakeside needs to decide. Meetings come with the updates Claude pulled from the transcript.

Claude read the OAC #11 transcript · Sep 24
5 suggested updates
Waiting for you to accept or reject
  • 13 Lift station: finish Nov 16 instead of Nov 11 (its transformer comes Nov 13)
  • New change on 14 Common area concrete: Saturday pour of the pool deck for Sandhill, about $2,900
  • New action item for Ridgeline: explain how the sand haul price in Change 16 was built

Grex to-dos

9

Action items for outside firms

3
  • Send the record drawings for the Section A and B sewer

    Why: The state needs them to clear the sewer for use.

    QuestionSep 23· 5 days late06Sanitary sewerDana· Ridgeline
  • Confirm the Section C sewer test date

    Why: Draw 6 holds the sewer amount until the test passes.

    QuestionSep 25· 3 days late06Sanitary sewerPriya· Harbor
  • Send the updated conduit drawings for Sections C and D

    Why: Ridgeline can't start the Section C and D conduit without them.

    QuestionOct 208Site electrical and street lightsNora· Electric utility

Needs Lakeside

3

Suggestions from Lakeside

Nothing changes until Grex accepts. Accepted and declined answers stay in the Impact Ledger.

2 waiting
  • Jordan· Sep 25· Whole project

    Hold Draw 6 until Harbor confirms the Section C sewer test.

  • Could Section A deliveries start Oct 12 instead of Oct 19? The plant has 8 homes ready early.

    H2 starts Oct 19 Oct 12