Vantage·Willow Creek Community — Phase 2
Schedule
BVersion B (with the builder's schedule)Data date Sep 28Started Aug 4, 2025Projected finishJul 30, 2027+5 working days
Drag a bar to move it · drag its end to change the finish
ProjectLine itemStartFinish
Jul
Aug
Sep
Oct
Nov
Dec
Jan 2026
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan 2027
Feb
Mar
Apr
May
Jun
Jul
Aug
71421284111825181522296132027310172418152229512192629162329162330613202741118251815222961320273101724317121926291623307141118251815221815222951219263101724317142128512192629162330No paving*Today · Sep 28
10 line items · $2.07M paid · Aug 2025 – Apr 2026
Mar 2026 – Jul 2027
EUElectric utilityU1Electric utility design and powerMar 2Oct 23*
SBSandhillB1Clubhouse and gatehouseApr 20Nov 13
RCRidgeline13Lift stationSep 8Nov 11
LDLakesideH2Home delivery and setOct 19Apr 23
LDLakesideH3Home finishing (hook-ups, skirting, decks and steps)Nov 2May 28
LDLakesideH4Driveways and walksDec 21Jun 18
LDLakesideH5Home site landscapingJan 18Jul 9
RCRidgeline12Asphalt, final courseMay 24Jun 11*
Other work14
RCRidgeline06Sanitary sewerMay 26Nov 3
RCRidgeline07Water main and servicesJun 8Nov 10
RCRidgeline10Road base and curbJul 6Dec 4
RCRidgeline15Home pads and building foundationsJul 20Mar 5
RCRidgeline08Site electrical and street lightsJul 27Dec 4
RCRidgeline09Cable and phone conduitAug 3Dec 4
RCRidgeline11Asphalt, first courseAug 17Dec 18
RCRidgeline17Restoration, sod and common landscapingAug 17Jun 25
RCRidgeline14Common area concreteSep 21Apr 23
CSCorvaleO2Maintenance garageNov 2Nov 13
RCRidgeline16Signs and site furnishingsMay 3May 21*
RCRidgeline19Cluster mailbox kiosksMay 10May 21*
NSNorthwoodsO1Picnic pavilionMay 10May 21*
NSNorthwoodsO3Resident storage sheds (24)Jun 7Jun 25*
Jun 14 – Jul 30
RCRidgeline18Testing, as-builts and closeout documentsJun 14Jul 2
GrexX1Final inspections, punch list and turnoverJul 12Jul 30*
Critical path Other work · fill = % done Done Milestone Approval waiting / granted* Assumed dateNo-work window TodayDrag a bar to move it