VantageWillow Creek Community — Phase 2 · Lakeside Development Co.
Files & Site
What the site looks like right now, the latest drone flight, the weather, and every document on the project.

LIVECam 1 · Section C work area
Mon, Sep 28Sep 28 ·
Counted by the camera today
16workers on site
2 excavators1 loader1 trencher
Ridgeline reported 18 · Kevin is checking the gap
Sep 15Today
Weather at the site
Lake Mirabel · logged daily, Grex can correct it
89°/ 74°
Today, Sep 28 · Light rain early, clearing
Rain
0.3 in
Wind
10 mph
Site
Working
Next 7 daysChance of rain · low / high
- TomorrowSep 2930%74°89°
- WedSep 3010%74°90°
- ThuOct 160%73°88°
- FriOct 220%72°87°
- SatOct 30%71°86°
- SunOct 420%72°88°
- MonOct 540%73°89°
Drone flight Oct 1: 60% chance of storms that day. Skyward flies the next dry morning if it rains.
Drone and site photos
Sep 1 flight · 16 photos · Skyward Site Imaging Next flight Oct 1
Documents
24 files · drawings, permits, contracts and reports, tagged by line item
Add filesDrop files here to add them
PDFs, drawings and photos. Vantage tags each one with its line item.
- PDFRidgeline pay request 6 (September)Other · Ridgeline · v1 · 450 KB · added by KevinWhole project· Sep 25
- PDFTurn-lane permit comments (street light)Permit · County · v1 · 5.1 MB · added by Kevin10Road base and curb· Sep 23
- XLSXRidgeline's September scheduleOther · Ridgeline · v4 · 1.8 MB · added by KevinWhole project· Sep 21
- PDFUpgraded skirting price: stone-look panels, $450 per home (Change 14)Other · Lakeside · v1 · 5.4 MB · added by Andrew
- PDFElectric layout, Sections C and D (utility, version 2)Drawing · Electric utility · v2 · 2.7 MB · added by Kevin
- PDFFire marshal review letter (two more hydrants)Other · County · v1 · 4.7 MB · added by Kevin07Water main and services· Sep 15
- PDFStandard deck and step plans, approved by the countyDrawing · Lakeside · v2 · 3.2 MB · added by Kevin
- PDFPad sign-off letter, Sections A and BReport · Harbor · v1 · 1.3 MB · added by Kevin
- PDFWater pressure and bacteria tests, Sections A and BReport · Harbor · v1 · 2.7 MB · added by Kevin07Water main and services· Aug 31
- PDFSewer test report, Sections A and BReport · Harbor · v1 · 4.8 MB · added by Kevin06Sanitary sewer· Jul 30
Rain days
Ridgeline's contract carries 10 a year. After that, rain means more time, not more money.
September so far
15
rain days
3
work stopped
43h
hours lost
Allowance10 of 10 used · ran out Jul 2
10 days the builder carries at its own risk+6 working days beyond it, logged as weather delays (Changes 6 and 13): time, not money1 more stopped day, made up on a Saturday: no working day lost
By monthRain daysWork stopped
Jul14 · 6 stopped
Aug13
Sep15 · 3 stopped
File requests
3 waiting · each one is also an action item
- Record drawings, Section A and B sewerRidgeline · Dana Whitfield5 days late
- Updated conduit drawings, Sections C and DElectric utility · Nora QuistDue Oct 2
- Insurance certificate (renewal)Sandhill · Rosa DelgadoDue Oct 9
- Pad sign-off letter, Sections A and BHarbor · Priya NairReceived Sep 9