Impact Ledger
Every change and why: which line item it hit, the reason, what caused it and who, and what it did to the cost, the draws and the finish date.
16 changes logged on 10 line items. Declined changes cost nothing.
- 12
- approved
- 3
- waiting on Lakeside
- 1
- declined$26K kept out
Totals by what caused it
Dollars added by each cause, approved and waiting. Click one to filter the ledger.
Weather added 6 working days at no cost to the owner. Switch to Days to see time by cause.
Why the budget moved
From the budget to the forecast final cost, step by step: the same bridge as the Dashboard.
$238,400 of changes − $184,260 because 34 other line items were priced below budget + $36,800 not in the owner's budget − $265,000 of contingency not used = $174,060 under budget.
Why by line item
Each change on each line item it touched, with its working days on that line and what reached the finish, plus costs the owner's budget did not plan for. Click a change to see its story.
- 04 Earthwork and gradingConstructionSigned price vs budgetBuilderBuilderRidgeline Civil−$31,000—
- 04 Earthwork and gradingConstructionWeather delayWeatherWeatherWeather (4 storm days)$0+3 days+3
- 05 Storm sewer and retention pondsConstructionChange orderEngineer or designerEngineer or designerHarbor Engineering (Priya Nair)+$14,600+2 days+2
- 06 Sanitary sewerConstructionSigned price vs budgetBuilderBuilderRidgeline Civil+$38,500—
- 06 Sanitary sewerConstructionOther delaySite conditionsSite conditionsFound by Ridgeline's crew; confirmed by Harbor Engineering+$42,600+4 days+4
- 06 Sanitary sewerConstructionWeather delayWeatherWeatherWeather (tropical storm)$0+3 days+3
- 07 Water main and servicesConstructionOther delayBuilderBuilderRidgeline Civil (Luis Ortega)$0+3 days+3
- 07 Water main and servicesConstructionChange orderTown, county or stateTown, county or stateThe county (fire marshal)+$16,900+1 day+1
- 07 Water main and servicesConstructionWeather delayWeatherWeatherWeather (tropical storm)$0+3 days+3
- U1 Electric utility design and powerConstructionOther delayTown, county or stateTown, county or stateThe electric utility (Nora Quist)$0+29 days · 5 to finish+295 to finish
- 08 Site electrical and street lightsConstructionOther delayTown, county or stateTown, county or stateThe electric utility (Nora Quist)$0+10 days+10
- 08 Site electrical and street lightsConstructionChange orderTown, county or stateTown, county or stateThe county (Greg Havel, right-of-way permits)+$11,400waiting—
- 13 Lift stationConstructionWeather delayWeatherWeatherWeather (tropical storm)$0+3 days+3
- 13 Lift stationConstructionChange orderBuilderBuilderRidgeline Civil (Dana Whitfield)+$16,800waiting—
- 14 Common area concreteConstructionChange orderOwnerOwnerJordan (Lakeside)+$23,800+3 days+3
- 15 Home pads and building foundationsConstructionSigned price vs budgetBuilderBuilderRidgeline Civil+$44,000—
- 15 Home pads and building foundationsConstructionOther delayGrexGrexKevin Quinn (Grex)+$3,200+1 day+1
- 19 Cluster mailbox kiosksConstructionNot in owner's budget—Ridgeline+$36,800—Quote, expires Nov 13, 2026
- H3 Home finishing (hook-ups, skirting, decks and steps)ConstructionChange orderOwnerOwnerJordan (Lakeside)+$57,600waiting—
Every change, and its story
Newest first. Changes recorded on the Schedule appear here as they happen; owner suggestions and their answers stay too.
- 16Sep 25, 2026 · recorded by Kevin Quinn (Grex)Waiting on owner
Ridgeline asks $16,800 to haul away extra sand from the lift station dig. Its price assumed the sand stays on site, but there is no room left to spread it.
- Price
- +$16,800
- Days
- None
- Finish date
- Unchanged
- Draw
- No draw moved
Learned from: Ridgeline's change request, Sep 25Needs Lakeside's answer. Jordan answers in her view, or Grex records an answer she gave by email. - Sep 25, 2026 · owner suggestion from Jordan (Lakeside)Waiting for Grex
“Hold Draw 6 until Harbor confirms the Section C sewer test.”
Whole projectAccepting records Grex's answer. - 15Sep 24, 2026 · recorded by Kevin Quinn (Grex)Waiting on owner
The county's turn-lane permit for the entrance needs a street light at the highway. Ridgeline priced the pole, fixture and conduit at $11,400.
08 Site electrical and street lightsChange orderTown, county or stateThe county (Greg Havel, right-of-way permits)- Price
- +$11,400
- Days
- None
- Finish date
- Unchanged
- Draw
- No draw moved
Learned from: County permit comments, Sep 23Needs Lakeside's answer. Jordan answers in her view, or Grex records an answer she gave by email. - Sep 23, 2026 · owner suggestion from Jordan (Lakeside)Waiting for Grex
“Could Section A deliveries start Oct 12 instead of Oct 19? The plant has 8 homes ready early.”
H2 Home delivery and setProposed dates Oct 12 – Apr 23Accepting moves the line item on the Schedule and logs the change. - 14Sep 22, 2026 · recorded by Andrew Chime (Grex)Waiting on owner
Lakeside asked for upgraded skirting on all 128 homes: insulated, stone-look panels instead of vinyl. Lakeside's finishing team priced it at $450 more per home.
- Price
- +$57,600
- Days
- None
- Finish date
- Unchanged
- Draw
- No draw moved
Learned from: Jordan's suggestion in Vantage, Sep 10Needs Lakeside's answer. Jordan answers in her view, or Grex records an answer she gave by email. - 13Sep 21, 2026 · recorded by Kevin Quinn (Grex)Approved
Tropical storm, Sep 15 to 17: 5.8 in of rain and flooded trenches. The site was shut for 3 working days and pumped out.
06 Sanitary sewer07 Water main and services13 Lift stationWeather delayWeatherWeather (tropical storm)- Price
- No cost
- Days
- +3 days
- Finish date
- Unchanged (Jul 30)
- Draw
- No draw moved
Learned from: Daily logs and weather log, Sep 15–17No cost to the owner: no answer needed. - 12Sep 18, 2026 · recorded by Kevin Quinn (Grex)Declined
Ridgeline asked $26,000 for weekend work to win back the sewer days lost to groundwater.
- Price
- +$26,000not spent
- Days
- None
- Finish date
- Unchanged
- Draw
- No draw moved
Learned from: Ridgeline's email, Sep 17Declined by Jordan, Sep 21: “Not approved: the sewer has float before it holds anything up, and winning the days back is Ridgeline's cost” - 11Sep 16, 2026 · recorded by Kevin Quinn (Grex)Approved
The county fire marshal asked for two more fire hydrants in Sections C and D when the site plan update was reviewed.
- Price
- +$16,900
- Days
- +1 day
- Finish date
- Unchanged (Jul 30)
- Draw
- No draw moved
Learned from: Fire marshal review letter, Sep 15Approved by Jordan, Sep 18: “Approved in Vantage”