VantageWillow Creek Community — Phase 2

Impact Ledger

Every change and why: which line item it hit, the reason, what caused it and who, and what it did to the cost, the draws and the finish date.

Live from the Schedule
Net effect of changes on cost
$0
$153K approved$85.8K waiting on Lakeside

16 changes logged on 10 line items. Declined changes cost nothing.

12
approved
3
waiting on Lakeside
1
declined$26K kept out
Effect on the finish date
+5working days since Version A
Jul 23 Jul 30, 2027

Totals by what caused it

Dollars added by each cause, approved and waiting. Click one to filter the ledger.

Weather added 6 working days at no cost to the owner. Switch to Days to see time by cause.

Approved Waiting on Lakeside

Why the budget moved

From the budget to the forecast final cost, step by step: the same bridge as the Dashboard.

Budget
Control budget
$14.42M
Change 14 · change order · Jordan (Lakeside)Waiting on Lakeside
+$57,600
Change 3 · signed above budget · Ridgeline Civil
+$44,000
Change 10 · other delay · Found by Ridgeline's crew; confirmed by Harbor Engineering
+$42,600
Change 1 · signed above budget · Ridgeline Civil
+$38,500
Change 2 · signed below budget · Ridgeline Civil
−$31,000
Other changes
6 more changes, some waiting on the owner
+$86,700
Savings
34 other line items priced below budget (before changes)
−$184,260
19 Cluster mailbox kiosks
+$36,800
Contingency not used
C1 and C2
−$265,000
Forecast final cost
$174,060 under budget
$14.24M

$238,400 of changes − $184,260 because 34 other line items were priced below budget + $36,800 not in the owner's budget − $265,000 of contingency not used = $174,060 under budget.

OwnerBuilderSite conditionsOther increasesSavings
Filter

Why by line item

Each change on each line item it touched, with its working days on that line and what reached the finish, plus costs the owner's budget did not plan for. Click a change to see its story.

Total = $238,400 of changes + $36,800 not in the owner's budget+$275,200

Every change, and its story

Newest first. Changes recorded on the Schedule appear here as they happen; owner suggestions and their answers stay too.

  1. 16
    Sep 25, 2026 · recorded by Kevin Quinn (Grex)
    Waiting on owner

    Ridgeline asks $16,800 to haul away extra sand from the lift station dig. Its price assumed the sand stays on site, but there is no room left to spread it.

    13 Lift stationChange orderBuilderRidgeline Civil (Dana Whitfield)
    Price
    +$16,800
    Days
    None
    Finish date
    Unchanged
    Draw
    No draw moved
    Learned from: Ridgeline's change request, Sep 25
    Needs Lakeside's answer. Jordan answers in her view, or Grex records an answer she gave by email.
  2. Sep 25, 2026 · owner suggestion from Jordan (Lakeside)
    Waiting for Grex

    “Hold Draw 6 until Harbor confirms the Section C sewer test.”

    Whole project
    Accepting records Grex's answer.
  3. 15
    Sep 24, 2026 · recorded by Kevin Quinn (Grex)
    Waiting on owner

    The county's turn-lane permit for the entrance needs a street light at the highway. Ridgeline priced the pole, fixture and conduit at $11,400.

    08 Site electrical and street lightsChange orderTown, county or stateThe county (Greg Havel, right-of-way permits)
    Price
    +$11,400
    Days
    None
    Finish date
    Unchanged
    Draw
    No draw moved
    Learned from: County permit comments, Sep 23
    Needs Lakeside's answer. Jordan answers in her view, or Grex records an answer she gave by email.
  4. Sep 23, 2026 · owner suggestion from Jordan (Lakeside)
    Waiting for Grex

    “Could Section A deliveries start Oct 12 instead of Oct 19? The plant has 8 homes ready early.”

    H2 Home delivery and setProposed dates Oct 12 – Apr 23
    Accepting moves the line item on the Schedule and logs the change.
  5. 14
    Sep 22, 2026 · recorded by Andrew Chime (Grex)
    Waiting on owner

    Lakeside asked for upgraded skirting on all 128 homes: insulated, stone-look panels instead of vinyl. Lakeside's finishing team priced it at $450 more per home.

    Price
    +$57,600
    Days
    None
    Finish date
    Unchanged
    Draw
    No draw moved
    Learned from: Jordan's suggestion in Vantage, Sep 10
    Needs Lakeside's answer. Jordan answers in her view, or Grex records an answer she gave by email.
  6. 13
    Sep 21, 2026 · recorded by Kevin Quinn (Grex)
    Approved

    Tropical storm, Sep 15 to 17: 5.8 in of rain and flooded trenches. The site was shut for 3 working days and pumped out.

    06 Sanitary sewer07 Water main and services13 Lift stationWeather delayWeatherWeather (tropical storm)
    Price
    No cost
    Days
    +3 days
    Finish date
    Unchanged (Jul 30)
    Draw
    No draw moved
    Learned from: Daily logs and weather log, Sep 15–17No cost to the owner: no answer needed.
  7. 12
    Sep 18, 2026 · recorded by Kevin Quinn (Grex)
    Declined

    Ridgeline asked $26,000 for weekend work to win back the sewer days lost to groundwater.

    06 Sanitary sewerChange orderBuilderRidgeline Civil (Dana Whitfield)
    Price
    +$26,000not spent
    Days
    None
    Finish date
    Unchanged
    Draw
    No draw moved
    Learned from: Ridgeline's email, Sep 17Declined by Jordan, Sep 21: “Not approved: the sewer has float before it holds anything up, and winning the days back is Ridgeline's cost”
  8. 11
    Sep 16, 2026 · recorded by Kevin Quinn (Grex)
    Approved

    The county fire marshal asked for two more fire hydrants in Sections C and D when the site plan update was reviewed.

    07 Water main and servicesChange orderTown, county or stateThe county (fire marshal)
    Price
    +$16,900
    Days
    +1 day
    Finish date
    Unchanged (Jul 30)
    Draw
    No draw moved
    Learned from: Fire marshal review letter, Sep 15Approved by Jordan, Sep 18: “Approved in Vantage”