Financials

What we expected to spend, what it is really costing, and why each line moved.

Data date Sep 28, 2026
Forecast final cost
$0
$174,060 under budget1.2% under the $14.42M budget
Paid
$6.08M
Signed, not paid
$7.25M
Not signed yet
$907K
Per home $111,268128 home sites · white tick = budget
Budget
$0
$112,627per home
Committed incl. approved changes
$0
$104,179per home
Paid
$0
$47,534per home
Over / under
$0under

7 line items over budget · 31 under, after changes

$1,360under per home

Spend over time

Paid so far against the Version A plan, then what is still to pay spread over the months its line items happen.

Version A planPaidForecast
Paid to date
$6.08M
$6,084,376 with proof of payment
Planned by the end of Sep
$7.45M
$1.37M behind the Version A plan
Still to pay
$8.16M
Signed, approved and projected, spread over the current dates
Forecast final cost
$14.24M
Budget $14.42M

Move a line item on the Schedule and its months move with it.

Cost report

By phase, then line item: the same line items as the Schedule. Click a line item to open it; click its over / under to see why.

Project totalknown costs
Budget
$14,416,300
Committed
$13,233,840
Approved changes
$101,100
Projected
$907,300
Paid
$6,084,376
Forecast final cost
$14,242,240
Over / under$174,060 under
Per home (128)$111,268 forecast · $112,627 budget

Unknown = no price yet: left out of the totals, never counted as $0. Not in owner's budget = a cost the owner's budget did not plan for. Owner buys = Lakeside pays it directly; its quote is under Contracts. Forecast final cost = committed + approved changes + projected. Paid counts only with proof of payment. Per home divides by 128 home sites.

Draw schedule

Payments the title company makes. Each draw is checked line by line against the builder's schedule of values before it is paid.

Paid through draws
$3.93M
7 draws, each with signed forms and proof of payment. Invoices are paid outside draws.
Draws still to pay

Contracts, quotes and invoices

Who gets paid, what is signed (committed), what is only quoted (projected), and one-off bills and fees.

Signed, current amount
$11.57M
Paid on signed contracts
$4.32M
Committed, unpaid
$7.25M
Quoted, not signed
$806K

Assumptions behind the numbers

What the forecast and the dates rest on. 5 still open; dates that rest on one are marked * on the Schedule.